Question # 17

True or False: Little's Law is used to forecast a Scrum Team's output.

A.

True

B.

False

Full Access
Question # 18

What should the Developers do if, during the Sprint, the Product Owner asks them to add an

urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work

in Progress (WIP) Limits?

(choose the two best answers)

A.

Add the urgent item to their Sprint Backlog but only start working on it when their

WIP Limits allow it.

B.

Adjust the WIP Limits to allow for taking on the extra item and record it as part of

their Definition of Workflow.

C.

Take on the urgent item as an exception to the WIP Limits and visualize that

they are above their WIP Limit.

D.

Reject the urgent item since the WIP Limits do not allow it. Tell the Product

Owner to wait until the next Sprint.

Full Access
Question # 19

Scrum Teams using Kanban can start to increase predictability by:

(choose the best answer)

A.

Visualizing the Workflow using a Kanban board.

B.

Improving transparency by having a CFD, Control Chart and Aging chart.

C.

Inspecting and adapting the Product Backlog during the Sprint Review.

D.

Reducing the amount of work in progress by introducing Work in Progress (WIP)

Limits.

Full Access