Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
At the beginning of Solution Development Timebox A, the Timebox is being
planned in detail. Although Foundations was conducted at a high level, the
Prioritised Requirements List was baselined. Now the Solution Development
Team is setting detailed acceptance criteria against each requirement.
Is this an appropriate approach to setting detailed acceptance criteria?
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company's
bank. These scripts will be used
to test the link from the
company's website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website's
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development
How should the Project Manager assist the plumbers to deliver the plumbing?
An external web developer is to be contracted to create the new coffee bar
insurance area on the existing web site. The chosen web developer will only
agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?