Question # 25

From the following list, which of the following apply to experience-based techniques? [K2]

a. Test cases are derived from a model of the problem to be solved or the software

b. Test cases are derived from the knowledge of the testers

c. The knowledge of testers, developers and users is used to drive testing

d. The internal structure of the code is used to derive test cases

A.

a and b.

B.

c and d.

C.

a and d.

D.

b and c.

Full Access
Question # 26

Test script TransVal 3.1 tests transaction validation via screen TRN 003B. According to the specification (PID ver 1.3 10b iv) the validation screen should not accept future dated transactions. Test script TransVal 3.1 passes. Test script eod 1.4 tests end of day processing and is run after the execution of TransVal 3.1 using data entered during that test

Which of the following is the BEST detail on an incident report? [K3]

A.

Title. End of Day failure.. Reproducible. Yes. Description. Script eod 1.4 fails when the first transaction of the day is a future dated transaction. Screen shot of the failure attached.

B.

Title. Transaction input screen validation..Reproducible. Yes. Description. Script eod 1..4 fails . Screen shot of the failure attached. Validation of transaction entryon screen TRN-003B should not allow future dated transactions – see PID ver 1.3 para 10b iv.

C.

Title. Screen TRN-003B validation of transaction date.. Reproducible. No. Description. When a future dated transaction is processed by the end of day process, a failure can occur. This does not always happen. Screen shot of the failure attached.

D.

Title. Screen TRN-003B validation of transaction date. Reproducible. Yes. Description. Script eod 1.4 fails when the first transaction of the day is a future dated transaction. Screen shot of the failure attached. Validation of transaction entry on screen TRN-003B should not allow future dated transactions – see PID ver 1.3 para 10b iv.

Full Access
Question # 27

Which of the following test design techniques is not a black box technique?

A.

Equivalence partitioning

B.

State transition testing

C.

Boundary value analysis

D.

Statement coverage

Full Access
Question # 28

What other details should be included in the following incident report when it is first submitted?

Date of Issue: 23/11/05

Severity: P1

Build: Version15.6

Details: Expected field to be limited to 15 chars, able to enter 27

A.

Suggested solution, priority and number of defects assigned to this developer.

B.

Status of the incident, degree of impact, Test Case Number.

C.

History, related defects and expected fix time.

D.

Line of code, number of defects found, time of day.

Full Access
Question # 29

Which of the following metrics could be used to monitor progress along with test preparation and execution? [K1]

A.

The total number of tests planned

B.

The total number of requirements to be tested

C.

The failure rate in testing already completed

D.

The number of testers used for test execution so far

Full Access
Question # 30

Which of the following test cases will ensure that the statement ‘Print ‘Hold’’ is exercised? [K3]

Refer to the exhibit

A.

X=2, Y=2, Z=2

B.

X=2, Y=3, Z=4

C.

X=2, Y=4, Z=3

D.

X=4, Y=3, Z=2

Full Access
Question # 31

What type of test design technique is the most effective in testing screen-dialog flows?

A.

Use case testing

B.

Boundary value testing

C.

Statement testing and coverage

D.

State transition testing

Full Access
Question # 32

Which statement correctly describes debugging? [K2]

A.

Testers identify defects, developers locate and correct defects, testers confirm the correction has cleared the original defect

B.

Developers identify defects, testers locate defects, developers correct and confirm the correction has cleared the original defect

C.

Testers identify and locate defects, developers correct defects and confirm the correction has cleared the original defect

D.

Developers identify, locate and correct defects, testers confirm the correction