Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

LEED-AP-BD+C Exam Dumps - LEED AP Building Design + Construction (LEED AP BD+C)

Go to page:
Question # 73

For Energy and Atmosphere Credit, Advanced Energy Metering, what is the minimum percentage requirement for metering any individual energy end uses?

A.

Those that represent 10% or more of the total annual consumption of the building

B.

Those that represent 25% or more of the total annual consumption of the building

C.

Those that represent 20% or more of the total annual consumption of the building

D.

Those that represent 15% or more of the total annual consumption of the building

Full Access
Question # 74

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

A.

The general contractor

B.

A LEED AP

C.

The project's mechanical engineer

D.

The owner or an owner's representative

Full Access
Question # 75

A developer is considering an urban infill site for a new commercial building rather than a rural greenfield site adjacent to a stream. Which of the following is an economic advantage of the infill site?

A.

Protects greenfields and farmland

B.

Preserves habitat and natural resources

C.

Reduces need for new utility infrastructure

D.

Reduces potential damage to an existing stream

Full Access
Question # 76

What aspects of each space should the LEED consultant consider to identify the regularly occupied spaces on a project to ensure that floor area values are utilized consistently across credits?

A.

Rate of outdoor air provided per person

B.

Fire ratings of installed wall and ceiling assemblies

C.

Average number of occupants standing or seated

D.

Typical duration of occupancy in each space per day

Full Access
Question # 77

In order to meet the minimum qualifications for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification a Commissioning (Cx) agent must have completed the commissioning process activities for a minimum of how many similar projects?

A.

Zero

B.

One

C.

Two

D.

Three

Full Access
Question # 78

An urban office building project is installing a cooling tower. To save on potable water, the project would like to use a nonpotable water source to provide 20% of the cooling tower makeup water to achieve the maximum number of points under Water Efficiency Credit, Cooling Tower Water Use. Which nonpotable water source would be the most appropriate for use?

A.

Municipally supplied tap water

B.

Ground surface stormwater runoff

C.

Rainwater collected from the building roof

D.

Graywater from the building's hand-washing sinks

Full Access
Question # 79

A contractor is building a retirement community project. 30% of the building's product costs were derived from reused/salvaged materials or met recycled content criteria. Which of the following credits can the LEED AP submit towards certification?

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials

B.

Materials and Resources Prerequisite, Construction and Demolition - Waste Management Planning

C.

Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients

D.

Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations

Full Access
Question # 80

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

Full Access
Go to page: