Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

LEED-AP-BD+C Exam Dumps - LEED AP Building Design + Construction (LEED AP BD+C)

Go to page:
Question # 41

What are the three phases within the Integrative Process Credit, Integrative Process?

A.

Pre-design, Discovery, Design and Construction

B.

Discovery, Design and Construction, Operations and Feedback

C.

Schematic Design, Design and Construction, Operations and Feedback

D.

Design Charrette, Schematic Design, Operations and Feedback

Full Access
Question # 42

The contractor has submitted waste hauling reports for review in order to achieve Materials and Resources Credit, Construction and Demolition Waste Management. Which of the following materials on the documentation contribute towards the credit?

A.

Excavated soil

B.

Wood derived fuel

C.

Items sent to the local incinerator

D.

Alternate Daily Cover

Full Access
Question # 43

Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?

A.

Floor decking

B.

Asbestos insulation

C.

Exterior glazing

D.

Plumbing fixtures

Full Access
Question # 44

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?

A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

Full Access
Question # 45

What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?

A.

LEED v4, LEED for Neighborhood Development Conditional Approval

B.

LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood Development Certified Project

C.

LEED for Neighborhood Development Pilot, Stage 1 LEED for Neighborhood Development Pre-reviewed Plan

D.

LEED 2009, Stage 1 Conditional Approval of LEED for Neighborhood Development Plan

Full Access
Question # 46

A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?

A.

Utility cost savings over the lifetime of the system must offset the higher initial cost

B.

Higher initial cost must exceed the cost of the utility over the lifetime of the system

C.

Higher initial cost must exceed the savings on the utility cost over the lifetime of the system

D.

Utility cost savings over the lifetime of the system must be lower than the higher initial cost of the system

Full Access
Question # 47

A project elects to pursue Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 2. Diverse Uses because of the project's location in an amenity-rich area. The project features 18 uses overall, including at least four uses in three of the five use type categories. What threshold must the project surpass in order to demonstrate exemplary performance for Option 2?

A.

Exemplary Performance is not available for Option 2

B.

15 uses, including two uses in each of the five categories

C.

15 uses, including at least one Food Retail and one Community Anchor use

D.

18 uses, including uses in at least four of the five use type categories

Full Access
Question # 48

A design team is working on a hospital project. In order to meet the Energy and Atmosphere Prerequisite, Minimum

Energy Performance, what option is used?

A.

Whole building simulation

B.

EPA target finder rating tool

C.

Green-e Energy

D.

Advanced building core performance guide

Full Access
Go to page: