Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-100 Exam Dumps - Certified Associate in Project Management (CAPM)®

Go to page:
Question # 49

Which of the following tools and techniques is used in the Verify Scope process?

A.

Inspection

B.

Variance analysis

C.

Expert judgment

D.

Decomposition

Full Access
Question # 50

Exhibit A is an example of which of the following types of Sequence Activities?

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Full Access
Question # 51

What are the identified risks for doing excessive decomposition in a WBS?

A.

Insufficient project funding and disqualification of sellers

B.

Insufficient project funding and ineffective use of resources

C.

Disqualification of sellers and non-productive management efforts

D.

Non-productive management effort and inefficient use of resources

Full Access
Question # 52

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Full Access
Question # 53

Which of the following is a strategy to deal with positive risks or opportunities?

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Full Access
Question # 54

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Full Access
Question # 55

The risk shared between the buyer and seller is determined by the:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Full Access
Question # 56

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Full Access
Go to page: