Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-PBA Exam Dumps - PMI Professional in Business Analysis

Go to page:
Question # 49

The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.

What should the team do to reduce the risk of rework?

A.

Ask the project sponsor to prioritize the requirements.

B.

Organize a new elicitation workshop.

C.

Perform a Pareto analysis on the requirements.

D.

Validate the requirements before continuing with development.

Full Access
Question # 50

Which of the following can be used to determine if requirements align to the product's objectives?

A.

Five Whys

B.

Activity network diagrams

C.

Context diagrams

D.

Business use cases

Full Access
Question # 51

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Full Access
Question # 52

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

A.

Time-boxing

B.

SWOT analysis

C.

Weighted ranking

D.

Multivoting

Full Access
Question # 53

A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?

A.

MoSCoW

B.

SMART goals

C.

RACI models

D.

Storyboarding

Full Access
Question # 54

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Full Access
Question # 55

The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?

A.

Prototype model

B.

Feature model

C.

Context diagram

D.

Use case

Full Access
Question # 56

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Full Access
Go to page: