A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?
A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
When selecting strategies as an activity of Plan Risk Response, what is the overall goal?
A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.
What should the risk manager do to handle this situation?