Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-RMP Exam Dumps - PMI Risk Management Professional (PMI-RMP) Exam

Go to page:
Question # 4

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

B.

Regularly check and report on the status of risks identified according to their prioritization.

C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Full Access
Question # 5

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Full Access
Question # 6

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

A.

During the project execution phase to allow the project manager to understand the risk attitudes of stakeholders.

B.

When a client project kick-off meeting is held to introduce risk assessment process to the client.

C.

Before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile.

D.

After a project budget is set up with a purchase order to charge hours for a risk workshop.

Full Access
Question # 7

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks' severity, and update the risk register.

Full Access
Question # 8

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Full Access
Go to page: