Question # 25

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Full Access
Question # 26

In what product should the quality criteria for a specialist product be recorded?

A.

Quality Management Strategy

B.

Quality Register

C.

Product Description

D.

Project Product Description

Full Access
Question # 27

During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

A.

Benefits Review Plan

B.

Product Status Account

C.

Business Case

D.

Project Plan

Full Access
Question # 28

Where should the names of those who are to approve a product be recorded?

A.

Product Status Account

B.

Product Description

C.

Configuration Item Record

D.

Checkpoint Report

Full Access
Question # 29

Which of the following statements about quality assurance and Project Assurance is true?

A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; qualityassurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Full Access
Question # 30

Which is NOT a purpose of a Benefits Review Plan?

A.

Define the periodover which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm anybenefits that are to be realised after the project is closed

Full Access
Question # 31

Which role is responsible for specifying the project benefits?

A.

Corporate or programmemanagement

B.

Executive

C.

Senior User(s)

D.

Project Manager

Full Access
Question # 32

Which is created during the Starting up a Project process?

A.

Project mandate

B.

Project management team role descriptions

C.

Communication Management Strategy

D.

Quality Register