Question # 33

Which is one of the three levels of plan in PRINCE2?

A.

Benefits Review Plan

B.

Programme Plan

C.

Team Plan

D.

Project Brief

Full Access
Question # 34

Which is NOT a PRINCE2 principle?

A.

Learn from experience

B.

Customer/supplier environment

C.

Defined roles and responsibilities

D.

Continued business justification

Full Access
Question # 35

Which is an objective of the Managing a Stage Boundary process?

A.

Understand what has gone well and what can help the next stage

B.

Review and approve the next Stage Plan

C.

Assure the Project Board that all project products have been completed and approved

D.

Prepare an Exception Report to advise the Project Board of aforecast deviation from tolerance

Full Access
Question # 36

Identify the missing words in the following sentence.

A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.

A.

any type of project

B.

programmes and projects

C.

all types of programmes

D.

business as usual

Full Access
Question # 37

Which statement about risks is FALSE?

A.

A risk that could have a positive impact on a project's objectives is known as an opportunity

B.

A risk that could have a negative impact on a project's objectives is known as a threat

C.

A risk that a project's product is incomplete is known as an off-specification

D.

A risk is an uncertain event that, should it occur, will have an effect on a project's objectives

Full Access
Question # 38

Which role is part of the project management team?

A.

Change Authority

B.

Quality assurance

C.

Stakeholder

D.

Corporate or programme management

Full Access
Question # 39

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A.

Benefits

B.

Quality

C.

Risk

D.

Scope

Full Access
Question # 40

Which is an objective of the Initiating a Project process?

A.

Develop the corporate quality management system as part of the Project Initiation Documentation

B.

Prepare the plans for the subsequentstages

C.

Summarize how the organization's project management method will be tailored for the project

D.

Request authority from corporate management to deliver the project

Full Access