Which role is part of the Project Board?
Corporate or programme management
Risk owner
Project Manager
Senior Supplier
QUESTIONNO: 223
Which describes risk appetite?
A. An organization's unique attitude towards risk-taking
B. The risks to the expected benefits
C. A common set of risk categories, risk scales and evaluation techniques
D. The budget set aside for potential changesto the scope of the project
Answer: A
Which is a typical core activity within configuration management?
Issue management
Quality inspection
Preparation
What theme estimates the cost of delivering the project?
Business Case
Change
Plans
Progress