(Select 2) What activity does NOT happen on Day 1 of PI Planning?
ROAMing of risks.
Assignment of business value.
Management review and problem-solving meeting.
Team breakouts.
Hourly checkpoints.
(Select 3) Who is typically involved in the ART Sync?
Scrum Masters
Product Owners
Business Owners
Release Train Engineer
Release Management
Solution Management
What is the target percentage for the Program Predictability Measure?
<50%
50-75%
80-100%
100%
None of the above.
What is the ideal size of an ART?
25 practitioners.
25-50 practitioners.
50-125 practitioners.
126-200 practitioners.
Whatever the Value Stream requires.
(select 2) What are the benefits of cadence and synchronization?
Synchronization enables multiple perspectives to be understood, resolved, and integrated at the same time.
They enable systems builders to operate reliably and with certainty within a safety buffer.
Synchronization enables reduction in WIP.
Cadence limits variance.
Cadence enables variability and makes wait times predictable.