SIAMP Exam Dumps - EXIN SIAM Professional Exam

Question # 4

ZYXS has been selected as the service integrator. The ZYXS Service Management and Service Desk Lead is the process owner of the change management process. Service providers are allowed to develop their own procedures. The IT Director has asked for a metric for the change management process that aligns with the SIAM principles of measurement

Which is the best metric?

A.

Amount of changes not submitted to the CAT on-time

B.

Consistent achievement of high-quality service provider changes

C.

Number of normal changes not recorded by the service provider

D.

Percentage of approved changes achieving the stated outcomes

Full Access
Question # 5

What best describes ZYX's strategic drivers for transitioning to a SIAM model?

A.

To enable the design implementation operation and improvement of integrated end-to-end services

•To ensure that these services are aligned with the ZYX corporate objectives, and allow problematic legacy systems to be retired

B.

To reduce the overhead and cost of managing an increasing number of service providers across the different ZYX companies

-To reduce the incidence of contract overlap, where more than one provider is being paid to deliver the same service within ZYX

C.

To reduce the risk of the service providers operating in silos, focused on their own targets rather than the wider end-to-end service

-To promote collaboration between providers in seeking ways to reduce IT operating costs and enable Agile development of new services C .

D.

To reduce the costs of operating IT. while at the same time ensuring that agreed service levels are met

-To enable IT capabilities that support agility and rapid expansion of the ZYX business into new geographical areas

Full Access
Question # 6

ZYX is initiating their NEWGEN SIAM transition project As part of the early planning, ZYX identifies key activities and milestones that must be included in the project plan.

What would be the best approach for ZYX to take in designing their SIAM governance framework?

A.

Define a framework of formally appointed governance boards with clearly documented terms of reference to act as decision making bodies, made up of representatives from all divisions of ZYX

B.

Ensure that the future service integrator's contract includes responsibility for establishing a governance framework that describes how the SIAM ecosystem will be managed and operated

C.

Establish a working group with representation from all ZYX divisions to review existing policies and practices, then define a framework of policies, standards processes, roles and structural elements

D.

Update the responsibilities of the IT Steering Group to include responsibility for ensuring that the SIAM ecosystem is implemented in accordance with defined plans and objectives

Full Access
Question # 7

ZYX has experienced a failure in their finance system leading to the delay of an invoicing run, a resulting temporary cash flow problem, and a breach of the service level for the end-to-end service.

Investigations show that this was caused by a change implemented by NETSCO A change request had been raised but not yet authorized As the NETSCO engineer thought it was urgent, they implemented the change without following the appropriate change processes to obtain authorization.

What is the most appropriate course of action the service integrator should take?

A.

Create a service improvement initiative for the treatment of emergency changes

B.

Impose service credits on NETSCO to compensate for the service level failure

C.

inform the management of NETSCO and let them deal with it as an operational matter

D.

introduce a service level target on changes implemented outside of the change control process

Full Access
Question # 8

The CIO is about to establish a project to transition ZYX to a SIAM operating model.

Which are the most important governance requirements to initially focus on, given the situation of ZYX?

A.

At this point in planning the transition project, the most important area for the CIO to focus on is strategic planning This includes building the SIAM business case reviewing legal requirements, identifying strategic nsks and ensuring a robust control structure is in place

B.

Before initiating the transition project designing and completing a detailed tooling strategy is critical for ZYX. This will help ZYX to select the service integrator and the service providers and will ensure a smooth onboarding of service providers into the integrated solution

C.

in order to ensure a smooth transition to the SIAM operating model, the CIO must focus on mitigating risks such as the ownership of tools, processes and data This is in order to prevent any loss of knowledge and skills as service providers are replaced

D.

The first task for the CIO is to establish governance over service levels and key performance indicators This will ensure that all contracts and agreements with SIAMRUS and the service providers are in place before transitioning to the SIAM operating model

Full Access
Question # 9

The CEO has asked the IT Director to create a SIAM strategy for ZYX that aligns with the mandate for change and the corporate strategy The CEO wants it as soon as possible.

What should the IT Director do?

A.

Adopt the SIAM strategy proposed by SIAMRUS for ZYX

B.

Adopt the SIAM strategy proposed by SIAMRUS for ZYXUK

C.

Design a new SIAM strategy ignoring the report from SIAMRUS

D.

Design a new SIAM strategy using the report from SIAMRUS as input

Full Access
Question # 10

One year ago. OUTSCO was appointed as the service integrator for ZYX. ZYXH provides the retained capabilities.

After a year of operating the SIAM model, OUTSCO has noticed that the 99 5% availability service level target for NEWBNK has been consistently overachieved by 0.4% every month.

In order to provide better value to ZYX and to challenge the service providers in their delivery, ZYXH would like to increase the availability target to 99 9% as soon as possible.

What is the best way of doing this?

A.

Ascertain the cost of the change from ZYXS, ZYXD and NETSCO and base the decision to proceed on a cost-benefit analysis

B.

Hold a meeting with ZYXS to discuss the feasibility of the increase and base the decision to change the target on their views

C.

Send an e-mail from OUTSCO to all service providers that the NEWBNK availability target is going to increase with immediate effect

D.

Tell ZYXS. ZYXD and NETSCO that the target is increasing and give them 3 months to make the necessary changes

Full Access
Question # 11

The ZYX Board of Directors decided that the proposal from SIAMRUS for ZYXUK was not suitable to be used for the whole of the group, and asked the ZYXS IT Director to lead the creation of a new SIAM strategy. This new SIAM strategy has now been approved by the NEWGEN Executive Steering Board.

What is the best approach to ensure that the ZYXUK Management Board supports the implementation of this SIAM Strategy?

A.

Delay the implementation of the strategy until the ZYXUK Management Board has formally approved it

B.

Ensure that each ZYXUK Management Board member is teamed with a member of the strategy team they know

C.

Ensure that the ZYXUK stakeholders understand how their perspective has been considered within the strategy

D.

Provide financial incentives to buy into the strategy for ZYXUK stakeholders who are not yet convinced

Full Access
Question # 12

The SIAM strategy for ZYX has been agreed:

-There will be a mix of new service providers and continuing existing service providers

-An external service integrator will be appointed

-ZYXS will provide the service desk.

-An agreement has been reached with OUTSCO to extend their contract to provide services to ZYXUK by two years

As key activities for the critical path to implement the SIAM model for ZYX, three parties must be transitioned into the SIAM model (listed in random order):

-continuing service providers

-the service integrator

-new service providers

In this instance, which sequence of activities offers the least risk to continuity of service for all ZYX companies'?

A.

All parties at the same time

B.

First the continuing service providers, then the service integrator and the new service providers last

C.

First the service integrator, then the new service provider, and the continuing service providers last

D.

First the service integrator, then both continuing and new service providers at the same time

Full Access
Question # 13

The ZYXS IT Director has proposed to the CIO that ZYXS should be the service integrator in the new SIAM model. The CIO wants to validate if the necessary capabilities exist in ZYXS. The CIO has asked SIAMRUS to perform the assessment.

What is the first activity that SIAMRUS should carry out?

A.

Compare the ZYXS service integration capabilities with the SIAM objectives and the target SIAM model

B.

Assess the existing capabilities of each team in ZYXS and determine if they are at the required maturity

C.

Identify and then map the stakeholders, process owners and managers for all services across ZYX

D.

Prepare a heat map to provide a graphical summary of capabilities and show it to the CIO

Full Access
Question # 14

ZYXS has been appointed as the service integrator ZYXH will provide the retained capabilities The CEO has asked the ZYXS IT Director to prepare a governance approach for monitoring and measuring service performance that will support the achievement of the strategic objective to ensure delivery against contracts.

What is the best approach?

A.

ZYXH will monitor the individual service providers with whom they have retained legal contracts and report the findings to ZYXS ZYXS will then integrate this with data gathered from its own contracted service providers to produce an end-to-end report

B.

ZYXH will review the performance of each delivered service in order to determine whether service levels have been achieved ZYXS will monitor its own performance, collect findings from the service providers, and collate these in a summary report to ZYXH

C.

ZYXS will assure delivery of the end to end service ZYXH will monitor the performance of ZYXS and overall achievement of the expected outcomes This includes ZYXH measuring the realization of benefits expected from the transition to SIAM

D.

ZYXS will monitor and measure each individual service provider for fulfilment of contractual targets. Based on reports from ZYXS. ZYXH will assume responsibility for monitoring the implementation of any improvements with the individual service providers

Full Access
Question # 15

ZYX has decided to appoint ZYXS as service integrator using the lead supplier structure ZYXS will need to fill new roles with additional skilled resources The contract with OUTSCO will be terminated, and all the component services will be transitioned to FIELD$CO: MAILSCO. NETSCO. ZYXD and ZYXS

The SIAM Project Board has just agreed that after the transition there will no longer be a requirement for service delivery managers in ZYXUK to manage the outsourced contract with OUTSCO

What is the best way to deal with this situation?

A.

Conduct a SIAM awareness campaign across all ZYX companies, briefing all staff about the benefits of moving to a SIAM model Ensure that the possibility of staff redundancies is not mentioned until the transition plan has been agreed

B.

Directly inform the two service delivery managers as soon as possible and invite them to Amsterdam to meet the ZYXS staff Ask them to be part of the team designing the SIAM model and encourage them to apply for the new roles

C.

inform the ZYXUK Directors of the situation and ask them to review the employment contracts of the service delivery managers. Once they are satisfied that there is no risk to sensitive data, inform the staff that their role will be redundant

D.

Leave the service delivery managers in uncertainty about whether their role will cease to exist or not. Offer them a financial incentive to be part of the transition team and stay with ZYXUK until the end if they decide they want to leave

Full Access
Question # 16

Project NEWGEN was completed against demanding timescales Because of time pressures, ZYX reduced the scope for testing of the end-to-end processes.

-SIAMRUS is the service integrator and also provider of the service desk for the SIAM ecosystem

-ZYXS is the internal service provider for NEWBNK, which is hosted by OUTSCO

-NETSCO provides the wide area network connecting the OUTSCO data center to the banks using NEWBNK.

Since the transition to SIAM, users of NEWBNK have experienced a significant increase in the time taken to fix incidents The ZYX sales team is now experiencing resistance from customers who were expected to migrate to NEWBNK This is affecting the planned rollout of the new application The ZYX sales team has told the customers that the issues were caused by the providers to ZYX not working together, and not the NEWBNK application itself.

What is the best approach for SIAMRUS to improve the situation?

A.

Design and implement a program of organizational change management and skills training with each service provider and measure the success of it

B.

Implement a new customer marketing campaign focusing on the benefits of NEWBNK and stress that the issues are temporary and will be resolved M|

C.

Implement Lean systems thinking in each provider to review and optimize the procedures, eliminating waste within the internal activities of the providers

D.

Use the process forums to mao analyze and improve the end to end processes assigning specific activities to appropriate mdividuals

Full Access