Which of the following is NOT an objective of a Retrospect Sprint Meeting?
A representative of the customer has asked the Development Team to add a very important item to an ongoing Sprint. What should they do?
The definition of done is an important principle in Scrum and something you must understand as a Scrum Master. Which one of the following statements is not a valid characteristic of the definition of done?
The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the
Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the
lessons learned during the process. What is an output of this process?
As a Scrum Master, it is important that you assess skill gaps and training requirements for the team members,
and map the skills, capabilities, and interest level of team members in using those skills and capabilities on a
project. Which one of the following tools can help you do this?