The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?
Which tools and techniques should a project manager use when estimating costs?
During what project management process does the project team begin identifying risks?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take to account for risk management n this environment’
How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?
Which key benefit can a project manager obtain by identifying stakeholders?