Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 169

The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?

A.

10 days

B.

15 days

C.

12.5 days

D.

5 days

Full Access
Question # 170

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

Full Access
Question # 171

A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?

A.

Project Resource Management

B.

Project Quality Management

C.

Project Schedule Management

D.

Project integration Management

Full Access
Question # 172

Which tools and techniques should a project manager use when estimating costs?

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Full Access
Question # 173

During what project management process does the project team begin identifying risks?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Full Access
Question # 174

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Full Access
Question # 175

How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?

A.

Adopt co-creation, sharing responsibilities with stakeholders

B.

Adopt participation of stakeholders in main meetings, listening to their opinion.

C.

Adopt social media tools, improving communication with stakeholders

D.

Adopt involvement of stakeholders in lessons learned sessions, sharing experiences with them

Full Access
Question # 176

Which key benefit can a project manager obtain by identifying stakeholders?

A.

Identify the appropriate focus for engagement of each stakeholder.

B.

Assess the risk exposure for each stakeholder.

C.

Map stakeholder power and influence grid.

D.

Identify the appropriate channels of communication with all stakeholders.

Full Access
Go to page: