Question # 161

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Full Access
Question # 162

For which kind of quantitative risk analysis chart can a tornado diagram represent values?

A.

Sensitivity analysis

B.

Monte Carlo analysis

C.

Expected monetary value analysis

D.

Decision tree analysis

Full Access
Question # 163

What can a project1 manager review to understand the status of project?

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Full Access
Question # 164

What process group includes processes performed to complete work to satisfy the project requirements defined in the project management plan?

A.

Initiating

B Executing

B.

Monitoring and Controlling

C.

Planning

Full Access
Question # 165

When can we say that a project is completed?

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

Full Access
Question # 166

Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

A.

Resource breakdown structure

B.

Physical resources assignment

C.

Team building activities

D.

Integrated Change Control

Full Access
Question # 167

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

A.

Iterative

B.

On-demand

C.

Interactive

D.

Quality

Full Access
Question # 168

Which of the following is used as input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Full Access