Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 185

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Full Access
Question # 186

When should quality planning be performed?

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Full Access
Question # 187

The Monitoring and Controlling Process Group includes processes that:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Full Access
Question # 188

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Full Access
Question # 189

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Full Access
Question # 190

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

A.

Develop Schedule

B.

Create VVBS

C.

Estimate Activity Resources

D.

Define Scope

Full Access
Question # 191

Tools and techniques used for Plan Communications include the communication:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Full Access
Question # 192

Which is used to solicit proposals from prospective sellers?

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Full Access