Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 193

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

A.

The receiver decodes the message

B.

The receiver responds to the message with feedback.

C.

The receiver transmits the message

D.

The receiver acknowledges their receipt of the message

Full Access
Question # 194

A construction project is underway, and during... tasks impacted the painting work

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?

A.

Finish-to-Finish (FF)

B.

Start-to-Finish (SF)

C.

Finish-to-Start(FS)

D.

Start-to-Slart(SS)

Full Access
Question # 195

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

Full Access
Question # 196

What is the purpose of the protect management process groups?

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Full Access
Question # 197

What is the number of stakeholders, if the project has 28 potential communication channels?

A.

7

B.

8

C.

14

D.

16

Full Access
Question # 198

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Full Access
Question # 199

Which of the following tools or techniques is used for Estimate Activity Durations?

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating

Full Access
Question # 200

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Full Access
Go to page: