A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
What type of project structure is a hierarchically organized depiction of the resources by type?