Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 257

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager. What should the project manager do to address this issue?

A.

Encourage the team to follow the project plan that was developed with team input.

B.

Apply emotional intelligence (EI) skills, such as active listening, to understand the team ' s issues.

C.

Instruct the team members to self-organize and resolve any outstanding issues.

D.

Ask the team members to record their concerns in the lessons learned log for future action.

Full Access
Question # 258

In which process might a project manager use risk reassessment as a tool and technique?

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Full Access
Question # 259

Change request status updates are an output of which process?

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Full Access
Question # 260

Which format can a network diagram take?

A.

Flow chart

B.

Control chart

C.

Affinity diagram

D.

Cause-and-effect diagram

Full Access
Question # 261

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Full Access
Question # 262

The project scope statement and resource calendars are inputs to which Project Time Management process?

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Full Access
Question # 263

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

A.

1

B.

0.4

C.

0.5

D.

0.8

Full Access
Question # 264

The activity tailoring is necessary because:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects

B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide

C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects

D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

Full Access
Go to page: