Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 289

The process of identifying specific actions to be performed to produce project deliverables is:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Full Access
Question # 290

Funding limit reconciliation is a tool and technique used in which process?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Full Access
Question # 291

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Full Access
Question # 292

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

A.

Two

B.

Four

C.

Five

D.

Twelve

Full Access
Question # 293

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

A.

0.8

B.

0.89

C.

1.13

D.

1.25

Full Access
Question # 294

The completion of the project scope is measured against the:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Full Access
Question # 295

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Full Access
Question # 296

What causes replanning of the project scope?

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Full Access
Go to page: