Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 249

Which is one of the determining factors used to calculate CPI?

A.

EV

B.

SPI

C.

PV

D.

ETC

Full Access
Question # 250

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Full Access
Question # 251

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Full Access
Question # 252

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Full Access
Question # 253

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Full Access
Question # 254

Risk exists the moment that a project is:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Full Access
Question # 255

The three processes of Project Cost Management are:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Full Access
Question # 256

Which of the following response strategies are appropriate for negative risks or threats?

A.

Share, Accept, Transfer, or Mitigate

B.

Exploit, Enhance, Share, or Accept

C.

Mitigate, Share, Avoid, or Accept

D.

Avoid, Mitigate, Transfer, or Accept

Full Access
Go to page: