Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 241

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

A.

Two

B.

Four

C.

Five

D.

Twelve

Full Access
Question # 242

Which of the following can be used as an input for Define Scope?

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Full Access
Question # 243

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.

event.

B.

response,

C.

perception.

D.

impact.

Full Access
Question # 244

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Full Access
Question # 245

Taking out insurance in relation to risk management is called what?

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Full Access
Question # 246

Which of the following is a tool and technique for Estimate Activity Durations?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Full Access
Question # 247

An input of the Control Schedule process is the:

A.

resource calendar.

B.

activity list.

C.

risk management plan.

D.

organizational process assets.

Full Access
Question # 248

An output of the Create WBS process is:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Full Access