Question # 169

An enterprise's internal audit group has scheduled a control review of a payroll system project but has been told to wait until the system is implemented. Which of the following is the GREATEST risk associated with the delay?

A.

delay in the development of new key performance indicators (KPIs)

B.

Continued dependency on compliant legacy systems

C.

Increased cost to mitigate deficiencies

D.

Lack of adherence to industry best practices

Full Access
Question # 170

Which of the following is an ADVANTAGE of using strategy mapping?

A.

It provides effective indicators of productivity and growth.

B.

It depicts the maturity levels of processes that support organizational strategy.

C.

It identifies barriers to strategic alignment and links them to specific outcomes.

D.

It depicts the cause-and-effect linked relationships between strategic objectives.

Full Access
Question # 171

An enterprise plans to implement a business intelligence (Bl) tool with data sources from various enterprise applications. Which of the following is the GREATEST challenge to implementation?

A.

Interface issues between enterprise and Bl applications

B.

Large volumes of data fed from enterprise applications

C.

The need for staff to be trained on the new Bl tool

D.

Data definition and mapping sources from applications

Full Access
Go to page: