Question # 65

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Full Access
Question # 66

Which of the following communication methods would be the most appropriate to finalize the handoff of deliverables?

A.

A virtual meeting with all the stakeholders

B.

A face-to-face kickoff meeting with the stakeholders

C.

A closure meeting with the project team and stakeholders

D.

A final report submitted via email to the stakeholders

Full Access
Question # 67

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Full Access
Question # 68

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

A.

Project dashboard

B.

Gap analysis

C.

Risk register

D.

Communication plan

Full Access
Question # 69

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Full Access
Question # 70

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).

A.

Purchase the materials.

B.

Assign the resources.

C.

Accept delays in the work.

D.

Approve the deliverables.

E.

Monitor the performance.

F.

Negotiate with the vendors.

Full Access
Question # 71

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Full Access
Question # 72

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

A.

XaaS

B.

SaaS

C.

PaaS

D.

laaS

Full Access