Question # 25

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Full Access
Question # 26

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

A.

Social

B.

Regulatory

C.

Environmental

D.

Governmental

Full Access
Question # 27

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Full Access
Question # 28

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Full Access
Question # 29

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Full Access
Question # 30

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Full Access
Question # 31

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Full Access
Question # 32

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Full Access