Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
Which of the following activities are performed during the closing phase? (Select three).
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
Which of the following requires the MOST availability from the business team?
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
Which of the following tools is best to use when conducting project meetings across time zones?
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
Which of the following software programs would be best to use to store information related to business transactions?
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
Which of the following can be used to determine whether a sample product is within an acceptable range?
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?
Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.
Which of the following is the current status of the process?
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
When assigning access, classifying information based on sensitivity is referred to as:
A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?
Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
Which of the following BEST illustrates how team members with different roles should interact on the team?
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
• Purpose
• Scope of work
• Location of work
• Period of performance
• Deliverables schedule
• Applicable standards
• Acceptance criteria
• Special requirements
• Payment schedule
Which of the following documents did the client provide to the project manager?
Which of the following is the best example of a breach of physical security?
A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?
During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).
A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
Which of the following can a project manager infer from the following velocity chart?
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?