Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PK0-005 Exam Dumps - CompTIA Project+ Certification (2024)

Go to page:
Question # 4

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Full Access
Question # 5

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Full Access
Question # 6

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Full Access
Question # 7

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Full Access
Question # 8

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Full Access
Go to page: