Question # 9

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Full Access
Question # 10

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

A.

The scope of the project deliverable is clearly defined

B.

There is a non-disclosure agreement in place

C.

There are multiple requirements for the product

D.

The PM wants to simplify the logistics of the required product

Full Access
Question # 11

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Full Access
Question # 12

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Full Access
Question # 13

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Full Access
Question # 14

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Full Access
Question # 15

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

A.

Allocate resources.

B.

Determine the project budget

C.

Develop a communication plan.

D.

Establish baselines.

Full Access
Question # 16

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Full Access