Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PK0-005 Exam Dumps - CompTIA Project+ Certification (2024)

Go to page:
Question # 49

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Full Access
Question # 50

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Full Access
Question # 51

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Full Access
Question # 52

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Full Access
Question # 53

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

A.

Removing access

B.

Closing contracts

C.

Project sign-off

D.

Project evaluation

Full Access
Question # 54

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Full Access
Question # 55

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Full Access
Question # 56

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

A.

Allocate resources.

B.

Determine the project budget

C.

Develop a communication plan.

D.

Establish baselines.

Full Access
Go to page: