A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Which of the following are placed at selected points in the work breakdown structure (WBS) for performance measurement?