Question # 73

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Full Access
Question # 74

What type of reward can hurt team cohesiveness?

A.

Sole-sum

B.

Win-lose

C.

Lose-win

D.

Partial-sum

Full Access
Question # 75

Which Knowledge Areas include processes from the Closing Process Group?

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Full Access
Question # 76

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

A.

Customers.

B.

Business partners.

C.

Sellers.

D.

Functional managers.

Full Access
Question # 77

Which of the following is a complete set of indexed contract documentation, including the closed contract?

A.

Procurement package

B.

Negotiated settlements

C.

Procurement file

D.

Procurement management plan

Full Access
Question # 78

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Full Access
Question # 79

During which process would stakeholders provide formal acceptance of the completed project scope?

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Full Access
Question # 80

When are deliverables accepted or not accepted?

A.

When the project is initiated

B.

As an output of the scope verification process

C.

When the project is closing

D.

In the contract closure process