Using the following data, what is the Schedule Performance Index (SPI)?
EV= $500 PV= $750 AC= $1000 BAC= $1200
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
Information collected on the status of project activities being performed to accomplish the project work is known as what?