Question # 81

Using the following data, what is the Schedule Performance Index (SPI)?

EV= $500 PV= $750 AC= $1000 BAC= $1200

A.

0.67

B.

1.5

C.

0.75

D.

0.5

Full Access
Question # 82

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

A.

Close Project or Phase

B.

Conduct Procurements

C.

Control Procurements

D.

Close Procurements

Full Access
Question # 83

In a weak matrix, the project managers role is:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Full Access
Question # 84

An input to Close Project or Phase is:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Full Access
Question # 85

Types of internal failure costs include:

A.

inspections.

B.

equipment and training.

C.

lost business.

D.

reworking and scrapping.

Full Access
Question # 86

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Full Access
Question # 87

The project management processes presented in the PMBOK Guide® should:

A.

always be applied uniformly.

B.

be selected as appropriate by the sponsor.

C.

be selected as appropriate by the project team.

D.

be applied based on ISO guidelines.

Full Access
Question # 88

Which statement correctly describes the value of a business case?

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Full Access