Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-001 Exam Dumps - Project Management Professional v5

Go to page:
Question # 113

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Full Access
Question # 114

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Full Access
Question # 115

Which tool or technique is used in the Estimate Costs process?

A.

Acquisition

B.

Earned value management

C.

Vendor bid analysis

D.

Forecasting

Full Access
Question # 116

What cost control technique is used to compare actual project performance to planned or expected performance?

A.

Cost aggregation

B.

Trend analysis

C.

Forecasting

D.

Variance analysis

Full Access
Question # 117

In Project Cost Management, which input is exclusive to the Determine Budget process?

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Full Access
Question # 118

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Full Access
Question # 119

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Full Access
Question # 120

Cost baseline is an output of which of the following processes?

A.

Estimate Activity Resources

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Full Access
Go to page: