Question # 89

Which of the following tools and techniques is used in the Verify Scope process?

A.

Inspection

B.

Variance analysis

C.

Expert judgment

D.

Decomposition

Full Access
Question # 90

An input to Develop Project Charter is a/an:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

Full Access
Question # 91

In which process group is the scope first defined?

A.

Initiating

B.

Planning

C.

Executing

D.

Controlling

Full Access
Question # 92

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Full Access
Question # 93

Which of the following is a tool and technique used in the Develop Schedule process?

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Full Access
Question # 94

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Full Access
Question # 95

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Full Access
Question # 96

Which of the following is an information gathering technique in Identify Risks?

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Full Access