Question # 49

To which process is work performance information an input?

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Full Access
Question # 50

The correct equation for schedule variance (SV) is earned value:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Full Access
Question # 51

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Full Access
Question # 52

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Full Access
Question # 53

What is a tool and technique used in the Develop Project Management Plan process?

A.

Project management information system (PMIS)

B.

Project charter

C.

Quality assurance

D.

Expert judgment

Full Access
Question # 54

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Full Access
Question # 55

Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

A.

Earned value performance

B.

Trend analysis

C.

Cost-benefit analysis

D.

Variance analysis

Full Access
Question # 56

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Full Access