Question # 57

Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?

A.

-8000

B.

-2000

C.

2000

D.

8000

Full Access
Question # 58

How many Project Management Process Groups are there?

A.

3

B.

4

C.

5

D.

6

Full Access
Question # 59

Which of the following is a tool or technique of the Define Activities process?

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Full Access
Question # 60

Verification of project deliverables occurs during which process?

A.

Develop preliminary project scope statement

B.

Close Project or Phase

C.

Develop project charter

D.

Create WBS

Full Access
Question # 61

Which activity may occur at project or phase closure?

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking

Full Access
Question # 62

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Full Access
Question # 63

The Closing Process Group includes which of the following Knowledge Areas?

A.

Project Risk Management and Project Procurement Management

B.

Project Integration Management and Project Procurement Management

C.

Project Risk Management and Project Integration Management

D.

Project Integration Management and Project Quality Management

Full Access
Question # 64

What is a technique used in the performance reporting process?

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Full Access