Question # 17

As a minimum requirement for applying the risk theme, what must specifically be assessed?

A.

Whether a risk may cause the project to exceed its cost tolerance

B.

Whether a risk may affect the project-level quality tolerances

C.

Whether a risk may impact the underlying technical assumptions

D.

Whether a risk may alter the project's business justification

Full Access
Question # 18

What must a PRINCE2 project demonstrate?

A.

Application of PRINCE2 principles

B.

Application of proper leadership skills

C.

Application of the activities in each process

D.

Application of tools appropriate for the industry

Full Access
Question # 19

Which is part of quality control?

A.

Undertaking quality reviews

B.

Writing product descriptions

C.

Providing assurance that the project is being conducted properly

D.

Documenting the customer's quality expectations

Full Access
Question # 20

Which should be provided by a project mandate?

A.

Terms of reference

B.

Detailed Business Case

C.

Stage tolerances

D.

Initiation Stage Plan

Full Access
Question # 21

What should be considered when defining the number of management stages in a project?

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Full Access
Question # 22

What is the project manager role responsible for?

A.

Approving the completion of each management stage

B.

Ensuring that the project produces the required products

C.

Defining the project-level tolerances

D.

Verifying that the project gives value for money

Full Access
Question # 23

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Full Access
Question # 24

Which are advantages of a clear end to a project?

1. No further costs will be incurred by the project

2. Project products will be transferred to operations and support

3. All benefits will have been achieved

4. The project brief will be re-baselined

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access