Question # 73

Which statement about the quality review technique is FALSE?

A.

It enables a check to be made on a product's fitness for purpose

B.

It defines the quality responsibilities of the project team

C.

It supports the management of future changes by providing a baseline for a product

D.

It is used to gain wider acceptance of a product by involving key interested parties

Full Access
Question # 74

How many roles make up the Project Board?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 75

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

A.

Executive

B.

Senior User

C.

Senior Supplier

D.

Project Manager

Full Access
Question # 76

Which is the purpose of the Change theme?

A.

Prevent change to baselined products

B.

Identify, assess and control any potential and approved changes to baselined products

C.

Establish mechanisms to monitor and compare actual achievements against those planned

D.

Assess and control uncertainty

Full Access
Question # 77

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

A.

Capture

B.

Examine

C.

Propose

D.

Decide

Full Access
Question # 78

Which is a difference between management and technical stages?

A.

Management stages require planning and technical stages do not

B.

Technical stages can overlap and management stages cannot

C.

Management stages deliver products and technical stages do not

D.

Technical stages require resources and management stages do not

Full Access
Question # 79

What theme estimates the cost of delivering the project?

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Full Access
Question # 80

Which is a purpose of the Controlling a Stage process?

A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products