Question # 97

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A.

Progress

B.

Change

C.

Organization

D.

Quality

Full Access
Question # 98

Which does NOT reflect the PRINCE2 principle of continued business justification?

A.

There must be a justifiable reason for starting a project

B.

The business justification drives decision making

C.

If a project is no longer forecast to deliver a financial benefit, it should be stopped.

D.

If a project can no longer be justified, it should be stopped

Full Access
Question # 99

Which is a purpose of the Controlling a Stage process?

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Full Access
Question # 100

What process aims to ensure accurate progress information is provided to the Project Manager?

A.

Starting up a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Full Access
Question # 101

How many tasks does the product-based planning technique describe?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 102

What product defines the reporting requirements between the Project Manager and Team Manager?

A.

Project Brief

B.

Product Description

C.

Team Plan

D.

Work Package

Full Access
Question # 103

Which is a purpose of a Project Product Description?

A.

Records the costs and timescales for delivery of the project's final product

B.

Shows the dependencies between the project's products to aid planning

C.

Provides a list of all the products to be delivered by the project

D.

Defines what the project must deliver in order to gain acceptance

Full Access
Question # 104

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

Full Access