Question # 65

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Full Access
Question # 66

In which step of the Issue management’ technique should Superseded versions be archives?

A.

Implementing changes

B.

Assessing issues

C.

capturing issues

D.

Deciding on changes

Full Access
Question # 67

How should the ‘progress’ practice be used?

A.

To define how the products will be delivered to enable control

B.

To predict whether the benefits will exceed the costs

C.

To identify opportunities that may make the project more successful

D.

To deliver change which will benefit people in their day-to-day work

Full Access
Question # 68

Which TWO are objectives of the ‘starting up a project’ process?

1. To create a common view of How the required quality will be achieved

2.To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 69

Which product identifies the management stages and timescales of a project?

A.

Project Brief

B.

Project Product Description

C.

Project Plan

D.

Initiation Stage Plan

Full Access
Question # 70

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Full Access
Question # 71

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

A.

quality

B.

supplier

C.

risk

D.

product

Full Access
Question # 72

Which is one of the three levels of plan in PRINCE2?

A.

Benefits Review Plan

B.

Programme Plan

C.

Team Plan

D.

Project Brief

Full Access