Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

Prince2-Foundation Exam Dumps - PRINCE2 7 Foundation written Exam

Go to page:
Question # 4

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

A.

Project mandate

B.

Initiation stage plan

C.

Project initiation documentation

D.

Project brief

Full Access
Question # 5

Which is a minimum requirement for applying the business case theme?

A.

To provide statements of actual benefits at benefits reviews

B.

To report on project performance at project closure

C.

To define the actions required to confirm the project's benefits are realized

D.

To monitor changes to the project plan to identify exceptions

Full Access
Question # 6

Which product identifies how often stakeholders require information?

A.

Communication management approach

B.

Lessons report

C.

Configuration item record

D.

Benefits management approach

Full Access
Question # 7

Which is a purpose of the plans theme?

A.

To identify, assess and control any potential changes to the baseline

B.

To establish the project's structure of accountability

C.

To assess and control uncertainty

D.

To understand whether the targets are achievable

Full Access
Question # 8

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

Full Access
Go to page: