Question # 113

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 114

What is a goal of the 'implement' step within the recommended risk management procedure?

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Full Access
Question # 115

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Full Access
Question # 116

The project manager has created a list of tasks to produce the project's products.

Which step of the ‘organizational design and development’ technique should be informed ty this 1st?

A.

Design the project ecosystem

B.

Understand the organizational ecosystem

C.

Manage the ongoing changes to the project ecosystem

D.

Develop the project ecosystem

Full Access
Question # 117

Which is a purpose of the quality theme?

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Full Access
Question # 118

According to the ‘exception management’ technique, when should the team manager raise an issue?

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Full Access
Question # 119

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

Full Access
Question # 120

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Full Access