Question # 121

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Full Access
Question # 122

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 123

Which principle helps to ensure that all changes to the outputs are agreed?

A.

Defined roles and responsibilities

B.

Focus on products

C.

Learn from experience

D.

Manage by exception

Full Access
Question # 124

Which statement about the length of management stages in a project is CORRECT?

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Full Access
Question # 125

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Full Access
Question # 126

Which describes a time-driven control?

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Full Access
Question # 127

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Full Access
Question # 128

What statement describes how the project manager should ensure effective communication within a project?

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Full Access