Question # 33

Program manager B leaves the program and program manager A takes over the program responsibilities Program manager A wants to ensure that all expected benefits of the program are realized.

What is used to assess the program cost/benefit justification?

A.

Program charter

B.

Benefits management plan

C.

Program business case

D.

Program scope statement

Full Access
Question # 34

A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?

A.

Rotate the responsibility for risk assessment among the program components

B.

Coach the project managers to manage project resources

C.

Cross-train the project managers to share expertise

D.

Prepare the project managers to assume larger roles with more responsibility.

Full Access
Question # 35

What is the MINIMUM fire rating for telecommunications spaces walls and wall linings, if not specified otherwise by local Authority Having Jurisdiction (AHJ)?

A.

One hour

B.

Two hours

C.

Three hours

D.

No minimum requirement

Full Access
Question # 36

Which of the following is a consideration for lighting telecommunication spaces?

A.

To ensure worker safety within TEs. Light level requirements are higher tor these than other spaces

B.

The light fixtures within telecommunications spaces shall be fluorescent type fixtures.

C.

The electrical power for lighting shall be connected to the same electrical panel as the telecommunications equipment.

D.

The lighting layout shall be coordinated with the equipment and pathway locations

Full Access
Question # 37

ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by

A.

coordinating with the job site supervisors

B.

issuing an RFI to the General/Prime Contractor

C.

texting or calling the General/Prime Contractor

D.

issuing a Change Order

Full Access
Question # 38

Which of the following transmitter light sources has a MINIMUM bandwidth of 4700 MHz/km (EMB) at 850 nm">

A.

OM1 (62 50/125 multimode)

B.

OM2 (50/125 multimode)

C.

OM3 (50/125 laser optimized multimode)

D.

OM4 (50/125 laser optimized multimode)

Full Access
Question # 39

In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?

A.

0.2 sq m (2 sq ft)

B.

0.5 sq m (5 sq ft)

C.

1 sq m (10 sq ft)

D.

1.5 sq m (16 sq ft)

E.

2 sq m (20 sq ft)

Full Access
Question # 40

During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the

A.

construction foreman

B.

legal counsel

C.

stakeholders

D.

technical consultant