Question # 4

A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap which consists of six program components Approval from the program governance board has been obtained.

What is the program manager's next step?

A.

Assign project managers and resources

B.

Classify the program's benefits

C.

Identify the program sponsor and program stakeholders

D.

Develop the program business case

Full Access
Question # 5

A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next"?

A.

Define the program architecture and assign the benefits realization to the component projects.

B.

Complete the program setup to establish a firm foundation of support and approval for the program

C.

Analyze lessons learned and historical information to validate the programs expected outcomes

D.

Continue to develop the high-level program road map

Full Access
Question # 6

What is the MAIN concern with a poke-thru installation?

A.

The compatibility with the telecommunications outlet/connector

B.

The structural integrity of the floor assembly

C.

The fact that it is beneath the floor

D.

The diameter of the poke-thru device

Full Access
Question # 7

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?

A.

Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups

B.

Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes

C.

Assess the risk of sustained negative media coverage

D.

Discuss the issues with the governance board to determine next steps

Full Access
Question # 8

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.

What should the program manager do next?

A.

Escalate the issue to the stakeholder's supervisor.

B.

Escalate the issue to the program governance board as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder, if unsuccessful, visit their office to identify potential risks