Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 97

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Full Access
Question # 98

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

Full Access
Question # 99

A project manager is newly assigned to a project. Which document can help the project manager understand the project scope?

A.

Process flow diagram

B.

Data flow diagram

C.

Context diagram

D.

User interface flow

Full Access
Question # 100

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Full Access
Question # 101

What internal enterprise environmental factor (EEF) can impact a project?

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Full Access
Question # 102

Construction of a building has stopped due to a supplier ' s failure to deliver concrete. The project schedule is behind by three months.

What should the project manager do to overcome this problem and put the project back on track?

A.

Follow the risk response plan and allocate resources, if needed, to overcome the issue.

B.

Consult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.

C.

Extend the time of product delivery and use management reserve to cover any losses.

D.

Accept any penalties that might occur and continue working as initially planned.

Full Access
Question # 103

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.

8

B.

18

C.

36

D.

40

Full Access
Question # 104

A project team member identifies a possibility......the team member ' s idea?

A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.

How should the project manager evaluate the team member ' s idea?

A.

Treat the idea using risk management processes, to handle it in a controlled and managed way.

B.

Perform an experiment simulation to confirm idea results, to make sure the cost to implement is worthwhile.

C.

Do a feasibility analysis study to confirm if an investment to explore a solution will add value.

D.

Submit the idea as a change request to the change control board to ensure that all interests are met.

Full Access