There are 50 stakeholders in the current project. How many communication channels exist in this project?
Which of the following process groups occurs at the beginning of the project?
The business sponsor of a project to automate a high risk, high profile process has expressed concerns that some activities people perform will be missed. The business analyst (BA) has already created a process flow with associated user stories.
Which of the following actions will address the sponsor’s concerns?
Which of the following roles works with the project team to understand the deliverables and then teaches the users of the deliverables how to utilize the project's product?
While reviewing a subset of requirements with stakeholders, a business analyst (BA) finds a requirement that does not deliver benefit to any of the stakeholders. After much discussion, the stakeholders decide that the requirement does not align with the solution scope.
What recommendation will the BA make?
An insurance company has two actuarial teams: Life and Non-Life. The Life team has a specialized tool to make their calculations while the Non-life team performs calculations manually. Last year the company bought a single solution to support both groups. The non-life team continues to do certain calculations manually to conform to their processes.
Which type of analysis was missed prior to purchasing a solution?
Which of the following describes the actual users who interact with one another, a system, or data moved between two users?
Which of the following charts is important to ensure that the roles and responsibilities of those involved in a task are tracked?