Question # 105

You are the business analyst for the NGQ Company. Management is concerned that their company is not able to meet an identified business need with their current existing structure, people, processes and technology. They've asked you to complete an analysis of their organization's ability to meet the identified business need.

What business analysis process are you completing for your organization?

A.

Determining the solution approach

B.

Assessing the capability gaps

C.

Requirements elicitation

D.

Verifying the requirements

Full Access
Question # 106

You are the business analyst for your organization and are working on prioritizing the project requirements. Management has asked you to prioritize the requirements based on the cost-benefit analysis for the requirements' value to the organization.

What basis for prioritization are you using in this instance?

A.

Business value

B.

Stakeholder agreement

C.

Likelihood of success

D.

Urgency

Full Access
Question # 107

You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis.

Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

A.

Change-driven approach

B.

Value-driven approach

C.

Plan-driven approach

D.

Requirements-driven approach

Full Access
Question # 108

When do change requests generally increase in a project?

A.

During the project's launch.

B.

Towards the beginning of the project.

C.

During the project scope management processes.

D.

Towards the end of the project.

Full Access
Question # 109

As part of the requirements analysis a business analyst can use the same tools and techniques to model the current state of an organization.

All of the following are valid reasons why would a business analyst want to create a current state domain model except for which one?

A.

The current state model can help identify opportunities for improvement.

B.

The current state model can help validate the solution scope with business and technical stakeholders.

C.

The current state model can help the business analyst create Pareto charts for process improvement.

D.

The current state model can help assist stakeholders in understanding the current state

Full Access
Question # 110

You are coaching Marcy, a new business analyst for your organization, on business analysis processes. Marcy is concerned about the define solution scope process, especially the implementation approach element.

Which of the following statements best defines the implementation approach element for Marcy?

A.

The implementation approach is described in terms of the major features and functions that are to be included.

B.

The implementation approach defines major business and technical dependencies that impose constraints to the effort to deploy the solution.

C.

The implementation approach describes the new capabilities required to meet the business need.

D.

The implementation approach describes how the chosen solution approach will deliver the solution scope.

Full Access
Question # 111

What business analysis process ensures that requirements specifications and models meet the necessary standard of quality to allow them to be used effectively to guide further work?

A.

Identify constraints and assumptions

B.

Validate requirements

C.

Verify requirements

D.

Specify and model requirements

Full Access
Question # 112

You are the business analyst for the TGH Organization and are determining if you should buy or build a solution for your company. You have determined that you can create the in-house solution for $78,000 with a monthly support cost of $8,765. A vendor can create the solution for $61,000 with a monthly support cost of $7,990.

How long will it take your company to break even if you choose the internal solution versus the vendor's solution?

A.

36 months

B.

12 months

C.

6 months

D.

22 months

Full Access