Question # 65

Gary is the business analyst for his organization and he is preparing a presentation about the requirements for a large software development project.

Before Gary makes the presentation what should he do as part of his preparation for the presentation?

A.

Determine an appropriate format for the presentation.

B.

Confirm that he has the authority to host the presentation.

C.

Confirm that the stakeholders have signed off on the requirements.

D.

Hire a scribe to keep the minutes of the meeting.

Full Access
Question # 66

You are working with Terry on the conduct stakeholder analysis task as part of the business analysis duties in your company. Terry wants to know why it's so important to identify stakeholders so early in the business analysis duties.

Which one of the following statements best addresses the need to identify the stakeholders early on in the business analysis duties?

A.

It's important to identify the stakeholders so the business analyst knows who to report to.

B.

It's important to identify the stakeholders so the business analyst knows who to bill for the project.

C.

It's important to identify the stakeholder so the business analyst can help ensure the timely delivery of the requirements deliverables.

D.

It's important to identify the stakeholders so the stakeholders know who the business analyst is.

Full Access
Question # 67

Gary is the business analyst for his organization. He has realized that he has overlooked a key group of stakeholders during the conduct stakeholder analysis process.

What is the danger in overlooking a key set of stakeholders?

A.

The newly identified stakeholders will now have to pay for any requirements they want to add to the requirements.

B.

The newly identified stakeholders will need to spend extra time to learn about the project and how it will affect them.

C.

The newly identified stakeholders will be excluded from decisions that affect the deliverables that have already been created in the project.

D.

The newly identified stakeholders may have requirements that require additions to the project or may nullify other requirements already in the project.

Full Access
Question # 68

Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?

A.

Pie chart

B.

Pareto Chat

C.

Critical Path Method

D.

Scatter chart

Full Access
Question # 69

A project's change in scope is assessed and a newly assigned business analyst (BA) is unsure how to communicate the findings and final decision to the wider stakeholder group.

In which of the following can the BA find this information?

A.

Stakeholder Communications Plan

B.

Business case

C.

Business policies

D.

Governance approach

Full Access
Question # 70

The business sponsor of a project to automate a high risk, high profile process has expressed concerns that some activities people perform will be missed. The business analyst (BA) has already created a process flow with associated user stories.

Which of the following actions will address the sponsor’s concerns?

A.

Record the concerns in the risk register

B.

Schedule a formal review with the stakeholders

C.

Demonstrate traceability to the business case

D.

Review the final approved elicitation results

Full Access
Question # 71

Which of the following process groups occurs at the beginning of the project?

A.

Executing

B.

Planning

C.

Initiating

D.

Controlling and Monitoring

E.

Closing

Full Access
Question # 72

The, an output of the define scope process, does document the process and criteria for accepting completed products.

A.

Statement of Work

B.

Contract

C.

Project scope statement

D.

Project management plan

Full Access